Promotion through the granting of subsidies for the improvement of school infrastructure in financially weak municipalities
LOGO
LOGO
Description of the
FD 23
Funding measure: Renovation of the BBS Aschersleben gymnasium
Reference number: 81348-184-SLK
Grant notification dated: 9 March 2020
Implementation period: 2021–2023
Description: As part of the school construction programme of the state of Saxony-Anhalt, the entire bitumen insulation roof and skylights, including the necessary smoke and heat extraction systems, of the gymnasium in Aschersleben were renovated and upgraded.
Financing:
Funding: € 643,500
Own funds: € 125,500
Total: € 769,000
Funding measure: Renovation of Burgschule secondary school in Aschersleben
Reference number: 81348-185-SLK
Grant notification dated: 19 March 2020
Implementation period: 2021–2023
Description: As part of the Saxony-Anhalt state school construction programme, the stairwells and entrance areas were renovated. In addition, fire safety and security deficiencies in the building (KG) were remedied as planned. Sports facilities and a small sports field were built in the outdoor area. The project was funded by federal funds.
Financing:
Funding measure: Renovation of the Otto Dorn special school in Bernburg
Reference number: 81348-188-SLK
Grant notification dated: 13 March 2020
Implementation period according to the grant notification: 1 July 2017 to 31 December 2025
Description: As part of the subsidy programme, the green roofs were renovated, windows and insulation in the old building were replaced, and escape and emergency route lighting (safety lighting) was installed. In addition, the gym was repainted and the sports floor was refurbished. The subsidy was provided by the federal government.
Financing:
Funding measure: Outdoor facilities at Friedrich Schiller Grammar School in Calbe
Reference number: 81348-182-SLK
Grant notification dated: 16 March 2020
Implementation period: 2021 - 2022
Description: As part of the Saxony-Anhalt state school construction programme, the area of approximately 1,650 m² that became available following the demolition of a building was converted into a school playground and sports field. The project was funded by the federal government.
The following measures were implemented:
Financing: