Applying for an extension of the building permit for the modification of an installation
Building applications - status enquiry
Extension of building permit (§ 71 in conjunction with § 63 BauO LSA)
Service description
If you have a valid building permit for the modification of an installation, you can apply for an extension of the building permit.
The competent lower building supervisory authority can extend the building permit by a maximum of one year.
Procedure
- You can apply for the extension of a building permit via the online service or in writing
- Proceed as follows for written applications:
- Submit the application and state which planning permission your application for an extension relates to.
- Submit the application to the responsible lower building supervisory authority.
- If necessary, the lower building supervisory authority will ask you to make an advance fee payment.
- Make the advance payment.
- If there are any ambiguities, you will be asked to resolve them.
- In this case, submit the clarification.
- The lower building supervisory authority will examine your application and involve the municipality and the necessary authorities.
- You will then receive notification of your application and a fee notice.
- Pay the fees.
Who should I contact?
Lower building supervisory authority
Prerequisites
You have a valid building permit for the modification of an installation.
The legal requirements have not changed in the meantime.
Which documents are required?
Application (via online service or in writing)
What fees are incurred?
Fees at least 50 €
The costs depend on the following factors:
- Construction costs
- Expenses for checking the building permit
What deadlines do I have to observe?
- You can apply for an extension of the planning permission as long as the planning permission is valid.
- Extension of the building permit by up to 1 year
Legal basis
Legal remedy
Contradiction
What else should I know?
You must submit a notification of commencement of use to the lower building supervisory authority at least 2 weeks before commencing use.